How Much Does It Cost to Convert a Garage Into an ADU in California?
Converting a garage into an ADU cost a median of $90,000, about $189 per square foot, in UC Berkeley's statewide survey of projects from 2018 and 2019, the only independent figure we could read. Prices have risen since, so treat it as a floor. The slab, the plumbing run and the electrical service decide where your garage lands.
What does a garage conversion ADU cost in California?
The best independent number is old, and it is still the place to start. UC Berkeley's Center for Community Innovation surveyed California homeowners who finished or applied for an ADU in 2018 and 2019. Its April 2021 report, Implementing the Backyard Revolution, found a median construction cost of $90,000 for garage ADUs, or $189.19 per square foot.
Garage units were the cheapest type in the survey on both measures. They also explain a regional quirk: Los Angeles County's median for all ADUs was $100,000, lower than every other region studied, and the authors point to garage conversions making up 39 percent of the county's ADUs against 11 to 14 percent elsewhere.
We could not retrieve a current independent survey for conversions, so the table below shows the Berkeley medians as published, with our own planning range beside them. Our ADU cost in California guide explains how that range was built.
Garage conversion ADU cost table, California
Survey rows are medians from UC Berkeley's 2021 report on projects from 2018 and 2019, exactly as published. The last row is MDG's own 2026 planning range, not a survey result.
| What it covers | Published figure | What to know |
|---|---|---|
| Garage ADU, statewide median | $90,000 ($189.19 per sq ft) | Includes conversions and expanded garages. The cheapest ADU type in the survey. |
| All ADU types, Los Angeles County | $100,000 ($197.22 per sq ft) | Garage units were 39 percent of the county's ADUs. |
| All ADU types, Orange and San Diego Counties | $130,000 ($200.00 per sq ft) | Small sample of 49 respondents for the two counties. |
| MDG planning range, garage to studio or one bedroom, 2026 | $100,000 to $200,000 | Our own range from the survey floor and current builder quotes. Assumes a sound slab and walls. |
How we got these numbers: the survey rows come from Table 2 of Implementing the Backyard Revolution (UC Berkeley Center for Community Innovation, April 2021), a 2020 survey of owners who completed or applied for an ADU in 2018 or 2019. Those costs are several years old. The last row is MDG's planning range from our ADU cost guide, with medium to low confidence. A written MDG proposal for your garage is the real price.
Why is a garage conversion cheaper than a detached ADU?
Because half the building already exists, and because state law waives several costs for conversions. In the Berkeley survey the median detached unit cost $180,000 and the median garage unit $90,000, a gap of $180,000 - $90,000 = $90,000. Per square foot it was $300.00 against $189.19.
The Department of Housing and Community Development's ADU Handbook, March 2026 edition, lists the legal savings.
- No setback is required for a unit created inside an existing accessory structure, so the garage stays where it is.
- No size cap applies to a conversion, and up to 150 square feet may be added for getting in and out.
- No solar system is required under the Energy Code for an ADU built within existing space. A newly built detached ADU does need one.
- No new-connection treatment: a unit built from existing space is not a new residential use for utility connection fees, unless it is built along with a new house.
- No impact fees at 750 square feet or less, as our impact fee guide explains.
A worked example: pricing a 20 x 20 two-car garage
A 20 x 20 garage is 400 square feet. At the survey's garage median of $189.19 per square foot, that is 400 x $189.19 = $75,676. At the Los Angeles County median for all ADU types, $197.22, it is 400 x $197.22 = $78,888. Both are 2018 and 2019 dollars.
The arithmetic cannot bring those dollars to 2026, and we found no independent index to do it. Treat $75,676 as a floor from several years ago and get a written proposal for today's price.
What does the building department make you fix in an old garage?
This list is where two similar garages end up with very different prices. LADBS Information Bulletin P/BC 2026-150, revised August 13, 2026, sets the minimums for a City of Los Angeles conversion.
- Slab: an existing slab may stay with an approved sealant as a moisture barrier. A slab that must be replaced means new concrete over a moisture membrane.
- Footings: existing ones may remain if free of excessive cracking. New footings go 24 inches deep on exterior walls and 18 inches on interior ones.
- Garage door opening: infilled with 2x4 studs at 16 inches on center.
- Bathroom: a separate one with toilet, sink and tub or shower, plus a 50 cubic feet per minute exhaust fan.
- Kitchen: sink, cooktop and refrigerator, each with 30 inches of clear space in front.
- Fire wall: a 1-hour rated wall where the unit has no sprinklers and stands less than 5 feet from the property line.
- Utilities: a separate electrical panel and a water shutoff valve inside the unit.
Los Angeles County's ADU guidelines (version 4.1, October 10, 2024) warn that garage fronts typically have no foundation under the door and that rafters are often undersized.
Does converting a garage mean building new parking?
No. The handbook cites Government Code section 66314(d)(11): when a garage, carport or covered parking structure is converted to an ADU, the local agency may not require that those off-street spaces be replaced. A separate rule, section 66322(a), bars a city from imposing parking standards on an ADU that is part of an existing accessory structure. The City of Los Angeles repeats both points in its ZA Memo 143.
Which permit path does your garage take?
The address decides, and the paths differ enough to change the soft costs. In the City of Los Angeles the conversion goes through LADBS plan check with a records search, and our garage conversion permit steps guide follows it stage by stage.
Unincorporated Los Angeles County offers a garage conversion ADU program with standard notes and details. A single-story garage with no added footprint, no unpermitted construction inside and no slope or liquefaction hazard may be eligible, and then needs no structural plans or calculations. It still needs approved architectural plans, Title 24 energy sheets and a pre-construction meeting with the inspector.
A garage in Burbank or Torrance follows that city's building department, with the same state rules on setbacks, parking and fees underneath.
What should a garage conversion bid spell out?
Ask for the bid in the order the inspector will look at the building, and have each line say whether it is a fixed price or an allowance. Conversions hide their problems under drywall and inside the slab.
MDG Builders, CSLB #1040337, takes ADU construction projects as a general contractor: we scope the garage, produce the plans and permit, and run the schedule, and the framing, plumbing, electrical and finish work is carried out by licensed subcontractors whose license numbers and insurance certificates you can ask to see. The unit will need a full bathroom, so the same fixture and waterproofing choices apply as in any bathroom remodeling job.
- Slab: keep and seal, or replace? What test or inspection decides it?
- Footing under the old garage door opening, and any underpinning.
- Plumbing run to the sewer line, in feet, and who trenches and patches.
- Electrical panel size and whether the main service needs an upgrade.
- Fire-rated wall, new windows and the egress door.
Garage conversion cost questions
How much does it cost to convert a garage to an ADU in California?
The median was $90,000, or $189.19 per square foot, in UC Berkeley's survey of 2018 and 2019 projects. That is a floor for today. For 2026 we plan on $100,000 to $200,000 for a sound two-car garage, and a failed slab, a long sewer run or a service upgrade moves a job toward the top.
Does converting a garage to an ADU add value?
It adds a legal rental unit, and we have no verified resale figure for conversions alone. In the Berkeley survey, garage ADUs rented for a median of $1,875 a month, or $3.47 per square foot, in 2020.
Do I need an architect for a garage conversion?
You need plans, though not always an engineer. Los Angeles County's garage program requires approved architectural plans but no structural plans or calculations when its standard notes are used and nothing is added. We did not confirm who is allowed to draw the plans in each city, so ask the building department.
Can I convert an unpermitted or detached garage?
A detached garage, yes: state ADU law expressly allows converting detached garages and other accessory structures. A garage with no permit on record is harder. Los Angeles County says it must be permitted as new construction and brought up to the current building code, including its foundation and framing.
Will I lose my driveway or parking?
You lose the covered spaces and keep the driveway. State law says a city cannot require replacement parking when a garage is converted to an ADU, and it cannot impose parking standards on a unit inside an existing accessory structure.
Does a garage conversion ADU need a new foundation in Los Angeles?
Not if the existing one is sound. LADBS lets existing footings and slabs remain when they are free of excessive cracking, with a sealant on the slab as a moisture barrier. New footings, for example under the old garage door opening where none exists, must be 24 inches deep on exterior walls.
Work that goes with this

ADU Construction
Garage conversions, detached ADUs and JADUs, with the 2026 permit clocks, utilities and sourced costs explained.
See ADU construction →
Concrete
Patios, driveways, walkways and retaining walls, poured by licensed specialists and priced from sources.
See concrete work →
Bathroom Remodeling
Showers, tubs, vanities and full baths, with the permit path, waterproofing and prices from named sources.
See bathroom remodeling →More garage conversion guides

Garage Conversion Permit Steps in Los Angeles
The permit path for turning a Los Angeles garage into an ADU, with the LADBS conversion checklist and the state deadlines.
Read the guide →
How Much Does an ADU Cost in California?
Sourced 2026 ranges for garage conversions and detached ADUs in Los Angeles, and how old the survey numbers are.
Read the guide →Do You Pay Impact Fees on an ADU Under 750 Square Feet?
What the 750 square foot exemption covers, what it leaves out (school, utility and permit charges), and the Los Angeles fee lines by name.