How Long Does an ADU Permit Take in Los Angeles?
An ADU permit in Los Angeles runs on two state clocks: the city has 15 business days to say whether your application is complete, then 60 days to approve or deny a complete one, under Government Code section 66317. Correction rounds, department clearances and your own response time decide how long it really takes.
What is the 60-day rule for ADU permits in California?
State law puts a deadline on the building department, not on you. The Department of Housing and Community Development's ADU Handbook, March 2026 edition, summarizes Government Code section 66317 this way: a permitting agency must approve or deny an application to create an ADU within 60 days of receiving a completed application, when the lot already has a single-family or multifamily home. The review is ministerial, which means staff check the plans against written standards with no hearing and no neighbor vote.
If the agency does neither within 60 days, the application is deemed approved. Los Angeles repeats the rule in its own guidance. The City Planning and LADBS ZA Memo 143, Revision 1, dated August 1, 2025, says LADBS, City Planning, LADWP and other local permitting agencies must act within 60 days of a complete application, including payment of fees.
A denial is a lawful answer inside the 60 days, as long as it comes in writing with a full list of defects and how to fix them. The rule promises a decision in 60 days, not a permit.
When does the 60-day ADU clock start?
It starts when the application is complete, and a second, newer clock governs that step. Since January 1, 2026, the agency has 15 business days from receiving your application to tell you in writing whether it is complete, according to HCD's summary of section 66317(a)(2). If the answer is no, the notice must list the missing items and describe how to complete the application. If the agency says nothing in 15 business days, the application is deemed complete.
Two more rules sit beside those clocks. You may ask for a delay for any reason, and the 60 days pause for as long as you asked. And if your application is found incomplete or is denied, the agency must offer an appeal and give a final written answer within 60 business days of your written appeal. At five business days a week, 60 business days is 12 weeks before holidays.
The handbook pages we read do not spell out how the clocks run after you resubmit corrected plans, so ask LADBS how it counts a resubmittal.
A worked example: counting the days on a Tarzana backyard ADU
Say a complete-looking set of plans for a detached unit reaches the city on Monday, March 1, 2027. Fifteen business days later is Monday, March 22, since three work weeks span 21 calendar days. By that date you should hold a written notice saying complete or incomplete.
Assume the application is complete on March 22. Sixty days on: 9 days left in March, 30 in April, and 21 in May, so the decision is due Friday, May 21, 2027. From submittal to decision that is 21 + 60 = 81 calendar days, a little under 12 weeks, if nothing is missing.
Now the common case. The city answers on day 50 with a denial and a correction list, and your designer needs three weeks to redraw. You have already spent 21 + 50 + 21 = 92 days before the second review starts. The legal clocks kept their promise and the calendar still slipped, which is why the first submittal matters most.
Which Los Angeles departments must clear an ADU before the permit issues?
Plan check is one line of several. LADBS Information Bulletin P/BC 2026-150, revised August 13, 2026, says clearances are generated during plan check and must be approved by the other departments before a permit and a Certificate of Occupancy are issued. The bulletin covers conversions and warns that clearances vary by parcel.
- Bureau of Engineering: a sewer availability clearance for all ADUs and JADUs, a roof drainage clearance when the site's drainage pattern changes, and an address clearance.
- LADWP: approval when the structure sits in a public utility easement or within 10 feet of one.
- Fire Department: hydrants and access.
- City Planning: a zoning clearance where the bulletin calls for one.
- Others: added by project location or site features.
What does LADBS need in the first ADU submittal?
A complete set of plans, plus proof of what already stands on the lot. The same bulletin sends applicants to Information Bulletin P/GI 2026-008 for the document list, which we did not read, and it names several items outright. If you are converting a garage, our garage conversion permit steps guide walks the conversion checklist in order.
- The Certificate of Occupancy and earlier building permits for any existing structure, so the plan checker can confirm its permitted use.
- The CF1R energy compliance certificate under Title 24, Part 6, attached to the plans.
- Los Angeles Green Building Code forms GRN 1, GRN 11, GRN 14 and GRN 16 as the new work requires.
- Foundation and framing details, since concrete footings and slab work get checked against the residential code.
- A site plan that shows the setback and height limits are met.
Do pre-approved standard plans speed up ADU plan check?
They shorten one part of it. The LADBS ADU page describes the Approved Standard Plan Program: private architects and engineers design plans that LADBS approves in advance for the building, residential and green codes. Pick one and LADBS still reviews your property, the zoning and the foundation. The department gives no number of days for the time saved, so neither do we.
Outside the city limits the path changes. Unincorporated Los Angeles County runs a garage conversion ADU program with standard notes and details. Its steps begin with Regional Planning approval of the architectural plans, then an application through EPIC-LA, an agency referral sheet, permit issuance and a mandatory pre-construction meeting with the County inspector. Homeowners in Glendale, Long Beach or Santa Clarita deal with their own city building departments, though the state clocks apply everywhere.
How long from ADU application to move-in?
Longer than the permit alone. UC Berkeley's Center for Community Innovation surveyed California owners who finished or applied for an ADU in 2018 and 2019 and asked how many months passed from the start of approval to completion. In its April 2021 report, Implementing the Backyard Revolution, 14 percent of 660 respondents finished within 5 months, 28 percent took 6 to 10 months and 25 percent took 11 to 15 months. That leaves 100 - 14 - 28 - 25 = 33 percent who needed 16 months or more.
Those projects predate the 2026 clocks and the sample is statewide, so read the spread as history. One more gate sits at the end: HCD's handbook says an owner must hold a Certificate of Occupancy before anyone lives in the unit, and LADBS issues it after the final inspection and clearances.
What can you control in an ADU permit schedule?
Three things: what you submit, how fast you answer, and what you choose to build. A design that stays inside the standards the state protects leaves less to argue about. MDG Builders, CSLB #1040337, works as the general contractor on ADU construction in Los Angeles: we coordinate the drawings, submit and track the permit and schedule inspections, and licensed subcontractors carry out the trade work once it issues.
Weighing a bedroom wing instead? A room addition goes through ordinary plan check, without these ADU deadlines.
- Pull the permit history first. A garage with no Certificate of Occupancy on file changes the plan-check conversation.
- Answer correction lists in one round, not three.
- Ask the plan checker which clearances your parcel triggers on day one, and start the slow ones early.
- In the coastal zone, expect a coastal development permit. HCD says it is reviewed on a 60-day clock of its own.
ADU permit timing questions
How long does it take to get an ADU permit in Los Angeles?
At best about 81 calendar days on paper: 15 business days for the completeness notice, then 60 days for a decision on a complete application. LADBS publishes no average that we could find. Correction rounds and other departments' clearances add to that.
What happens if ADU permits take longer than expected?
If the city misses the 60-day deadline on a complete application, the application is deemed approved under Government Code section 66317, as HCD's March 2026 handbook explains. If the city said your application is incomplete or denied it, you can appeal in writing, and the city owes a final written answer within 60 business days.
What is California's new ADU law for 2026?
The main permit change is a set of deadlines that took effect January 1, 2026. Agencies must issue a written completeness notice within 15 business days, list every missing item, and offer an appeal that ends within 60 business days. HCD's handbook also notes that size limits are now measured in interior livable space.
Do I need a permit to build an ADU in California?
Yes. Every ADU needs a building permit, and state law requires that the permit be reviewed ministerially, without a public hearing. HCD's handbook adds that you must obtain a Certificate of Occupancy before anyone lives in the unit.
Are Los Angeles pre-approved ADU plans cheaper and faster?
Faster in plan check, according to LADBS, though the department gives no figure. Standard plans are pre-approved for the building, residential and green codes, and LADBS still reviews zoning and the foundation for your lot. We found no official cost comparison, so ask what site-specific drawings you would still pay for.
How long does it take to build an ADU in Los Angeles?
Most take more than half a year from the first application to completion. In UC Berkeley's statewide survey of 2018 and 2019 projects, 14 percent finished within 5 months, 28 percent took 6 to 10 months and 25 percent took 11 to 15 months. We found no official Los Angeles figure for construction alone.
Work that goes with this

ADU Construction
Garage conversions, detached ADUs and JADUs, with the 2026 permit clocks, utilities and sourced costs explained.
See ADU construction →
Room Additions
Family rooms, primary suites and second stories, from zoning check to final inspection, with sourced prices.
See room additions →
Concrete
Patios, driveways, walkways and retaining walls, poured by licensed specialists and priced from sources.
See concrete work →More ADU permit guides

Garage Conversion Permit Steps in Los Angeles
The permit path for turning a Los Angeles garage into an ADU, with the LADBS conversion checklist and the state deadlines.
Read the guide →How Close to the Property Line Can You Build an ADU in California?
The 4-foot side and rear rule, the 16, 18 and 25 foot height floors, the size caps a city cannot go below, and a lot-fit example.
Read the guide →Do You Pay Impact Fees on an ADU Under 750 Square Feet?
What the 750 square foot exemption covers, what it leaves out (school, utility and permit charges), and the Los Angeles fee lines by name.